The renovation is done.
Work Stages:
1. Wallpaper removal
2. Wall priming
3. First layer of putty
4. Sanding
5. Re-priming
6. Second layer of putty
7. Sanding
8. Re-priming
9. Third (final) layer of putty
10. Sanding
11. Re-priming
12. First coat of paint
13. Second coat of paint
14. Ceiling painting
15. Seam finishing
16. Cleaning and debris removal
⸻
Timeline:
Work started in February
Duration: 2 months (including drying time between stages)